Question: Work performance information is considered as A. A necessary process to enter a contract B. Required as part of the vendor performance evaluation C. Only


Work performance information is considered as A. A necessary process to enter a contract B. Required as part of the vendor performance evaluation C. Only needed for contracts in distress D. An output from the direct and manage project execution process