Question: A mining company is planning to construct an underground coal mine within a thin coal seam that dips 2 due east. You are the mine
A mining company is planning to construct an underground coal mine within a thin coal seam that dips 2° due east. You are the mine engineer, and it is your task to make sure that the mine adits do not fill with water. This requires that each adit has a slope of no less than 1°. In what directions may adits be oriented within the coal seam such that their slope is 1° or steeper?
Step by Step Solution
3.38 Rating (148 Votes )
There are 3 Steps involved in it
To ensure that each adit has a slope of no less than 1 within the thin coal seam we ca... View full answer