For Rambler Manufacturing in problem 49, suppose that sales of clutch plates 1, 2, and 3, respectively

Question:

For Rambler Manufacturing in problem 49, suppose that sales of clutch plates 1, 2, and 3, respectively are 180, 300, and 200 units for the week, and workstation C works two shifts for a total of 90 hours this week. What is the workload in hours for the week on workstation C and what is workstation C’s utilization? Can workstation C fulfil the week’s sales?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  answer-question
Question Posted: