Question: Using the network diagram constructed in Problem 1, (a) Calculate the completion time for the project. (b) Determine which activities are included on the critical
(a) Calculate the completion time for the project.
(b) Determine which activities are included on the critical path.
.png)
Immediate Predecessor(s) none Activity Time Activity (weeks) 4 E, F