Question: In problem 37, suppose the line is balanced using 14 workstations and a finished product can be produced every 4.5 minutes. a. What is the

In problem 37, suppose the line is balanced using 14 workstations and a finished product can be produced every 4.5 minutes.

a. What is the production rate in units per day?

b. What is the assembly line efficiency?

Step by Step Solution

3.43 Rating (156 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Using Equation 82 CT AR or 45 480R or R 1... View full answer