LCD Software must complete the project defined by the following network in 22 weeks. The expected times

Question:

LCD Software must complete the project defined by the following network in 22 weeks. The expected times and the activity variances are shown in the table below.image text in transcribed

image text in transcribed

a. Find the critical path(s) and compute the probability of completing the project by week 18.

b. Draw a Gantt chart for the project.

Step by Step Answer:

Related Book For  answer-question