Question: 15. Use a spreadsheet program to develop the MRP records for parts A and B from the following product structure. Use the data from the
15. Use a spreadsheet program to develop the MRP records for parts A and B from the following product structure. Use the data from the following table:
Part A B Requirements 50/period —
Initial inventory balance 63 8 Lead time 1 1 Lot size lot-for-lot 250 Safety stock 10 —
Scheduled receipt — 250 in period 1
a. What are the planned orders for item B?
Step by Step Solution