Question: 8. (**) Just before starting the project described in Problem 7, someone points out that (1) Activity A really needs to be done before Activity
8. (**) Just before starting the project described in Problem 7, someone points out that (1) Activity A really needs to be done before Activity C, and (2) Activity C needs to be completed before Activity G can start. What is the impact on the expected length of the project?