Question: Distribution requirements planning (DRP) provides a link between a. Master production scheduling (MPS) and material requirements planning (MRP) b. Internal and external manufacturing planning and
Distribution requirements planning (DRP) provides a link between
a. Master production scheduling (MPS) and material requirements planning
(MRP)
b. Internal and external manufacturing planning and control (MPC) systems
c. Material requirements planning (MRP) and vendors
d. Sales and operations planning and vendors