Question: In a system with a forecast mean absolute deviation (MAD) of 100 units (over the lead time), what level of safety stock would be required
In a system with a forecast mean absolute deviation (MAD) of 100 units (over the lead time), what level of safety stock would be required to ensure that 90 percent of order cycles have no stockouts? (Choose the best answer.)
a. 140 units
b. 150 units
c. 160 units
d. 170 units
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts