Question: 4. You're a project manager for a construction project. You don't control the project budget, the team doesn't report to you, and you routinely have
4. You're a project manager for a construction project. You don't control the project budget, the team doesn't report to you, and you routinely have to request their time from their manager. What kind of organization do you work in? A. Functional B. Weak matrix C. Strong matrix D. Projectized