Question: 7. Susan is project manager on a construction project. When she hears that her project has run into a snag due to weeks of bad
7. Susan is project manager on a construction project. When she hears that her project has run into a snag due to weeks of bad weather on the job site, she says “No problem, we have insurance that covers cost overruns due to weather.” What risk response strategy did she use?
Exploit Transfer Mitigate Avoid
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts