Question: For the periodic processes given below, find a valid schedule a. using standard RMS; b. adding one unit of overhead for each context switch. 22

For the periodic processes given below, find a valid schedule

a. using standard RMS;

b. adding one unit of overhead for each context switch.

22 P2 P1 P3 Process P1 P2 P3 Time Deadline 2 30

22 P2 P1 P3 Process P1 P2 P3 Time Deadline 2 30 57 40 120 P4 5 60 P5 1 15