Question: 4. The optimal sequence for an n-job, 2-machine problem implies that the sequence of performance of jobs which would ensure their completion in the minimum
4. The optimal sequence for an n-job, 2-machine problem implies that the sequence of performance of jobs which would ensure their completion in the minimum time as well as minimisation of idle time on the second machine.Mark the statement as T (True) or F (False).