Question: Prepare an Early Start schedule for the network shown. Indicate the allowable time span for each activity. Activity durations are in days. 1 9 2

Prepare an Early Start schedule for the network shown.

Indicate the allowable time span for each activity. Activity durations are in days.1 9 2 7 6 7 5 5 8 13 15 13

1 9 2 7 6 7 5 5 8 13 15 13 3 9 3 4 7 8