Question: Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in
Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for (1) cutting and sewing and (2) delivery of each of the suits. Which schedule finishes sooner: First-come, first-served (123 or a schedule using Johnsonsrule?
.png)
Times Taken for Different Activities (hours) Cut and Sew 4 Suit Deliver
Step by Step Solution
3.27 Rating (159 Votes )
There are 3 Steps involved in it
Johnsons Rule finishes in 21 days 2 days faster than ... View full answer