Question: Suppose that a lean work center is being operated with a lot size of 50 units. Assume that 200 parts are demanded per hour and

Suppose that a lean work center is being operated with a lot size of 50 units. Assume that 200 parts are demanded per hour and it takes three hours to circulate a container, including all setup, run, move, and idle time.
a. Calculate the number of kanban containers required.
b. What is the maximum inventory that will accumulate?
c. What can be done to reduce the inventory level? Suggest alternatives.

Step by Step Solution

3.30 Rating (165 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a n DTC 200hour3 hrs50 unitscontainer 60050 12 con... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

555-B-M-L-S-C-M (3463).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!