Table considers the development of a short course in project management. From the information, construct the network

Question:

Table considers the development of a short course in project management. From the information, construct the network diagram.
(a) Determine the ESTs, the LSTs, the project duration and the critical path activities.
(b) Show the slack for each activity.
(c) What further factors should be considered in order to give a better view of the realistic timescale for the organisation of thecourse?