Question: Ten years ago, the port of Secoma built a new pier containing a large amount of steel work, at a cost of $300,000, estimating that

Ten years ago, the port of Secoma built a new pier containing a large amount of steel work, at a cost of $300,000, estimating that it would have a life of 50 years. The annual maintenance cost, much of it for painting and repair caused by environmental damage, has turned out to be unexpectedly high, averaging $27,000. The port manager has proposed to the port commission that this pier be replaced immediately with a reinforced concrete pier at a construction cost of $600,000. He assures them that this pier will have a life of at least 50 years, with annual maintenance costs of not over $2,000. He presents the information in Table PI 0-22 as justification for the replacement, having determined that the net market value of the existing pier is $40,000.
He has stated that, because the port earns a net profit of over $3,000,000 per year, the project could be financed out of annual earnings. Thus, there would be no interest cost, and an annual savings of $19,000 would be obtained by making the replacement.
a. Comment on the port manager's analysis.
b. Make your own analysis and recommendation regarding the proposal.

Step by Step Solution

3.47 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a The port managers analysis is in error due to failure to consider the time value of money Whet... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

929-B-F-R-A (997).docx

120 KBs Word File

Students Have Also Explored These Related Finance Questions!