Question: Teradyne Connection Systems makes backplanes (large printed circuit-board assemblies) for communication and storages devices. Recently, the company converted its production process from batch into assembly

Teradyne Connection Systems makes “backplanes” (large printed circuit-board assemblies) for communication and storages devices. Recently, the company converted its production process from batch into assembly line, [t also used computers to assist the workers at workstations. As a result, productivity has shot up. The site manager, Mark Galvin, says: “Operators made 300 backplanes in seven days using three shifts by a batch process (i.e., 7 days, 24 hours a day). Later, they assembled 500 backplanes in five days using just two shifts with the new assembly-line approach (i.e., 5 days, 16 hours a day).” Assuming that the same number of workers worked during each shift, and before and after the conversion, what is the percentage growth in labour productivity?

Step by Step Solution

3.38 Rating (160 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Let N no of workers per shift Before Labour productiv... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

686-B-M-L-O-M (4593).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!