Question: The average part produced in a certain batch manufacturing plant must be processed sequentially through six machines on average. Twenty (20) new batches of parts

The average part produced in a certain batch manufacturing plant must be processed sequentially through six machines on average. Twenty (20) new batches of parts are launched each week. Average operation time = 6 min., average setup time = 5 hours, average batch size = 25 parts, and average non operation time per batch = 10 hr/machine. There are 18 machines in the plant working in parallel. Each of the machines can be set up for any type of job processed in the plant. The plant operates an average of 70 production hours per week. Scrap rate is negligible. Determine
(a) Manufacturing lead time for an average part,
(b) Plant capacity,
(c) Plant utilization.
(d) How would you expect the non operation time to be affected by the plant utilization?

Step by Step Solution

3.39 Rating (158 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a MLT 65 2501 10 105 hr b T p 5 25 x 0125 030 hrpc R p 3333 pchr PC 701833336 700 pcweek c P... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

795-C-S-A-I (368).docx

120 KBs Word File

Students Have Also Explored These Related Artificial Intelligence Questions!