Question: The data in Table 8E.11 were taken by one operator during a gauge capability study. (a) Estimate gauge capability. b) Does the control chart analysis
.png)
(a) Estimate gauge capability.
b) Does the control chart analysis of these data indicate any potential problem in using the gauge?
TABLE 8E.11 Measurement Data for Exercise 8.33 Part Measarements Part Namber I 2 Number 20 19 20 21 2 24 20 21 2 25 26 18 17 16 15 20 20 23 22 2822 19 25 21 20 20 21 18 18 i0 12 13 14 15 5 6
Step by Step Solution
3.49 Rating (162 Votes )
There are 3 Steps involved in it
a Gauge capability 6 68154 b An... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
593-M-S-S-I (3406).docx