Question: The following data reflect the current months activity for Sills, Inc.: Actual total direct labor . . . . . . . . . .
The following data reflect the current month’s activity for Sills, Inc.:
Actual total direct labor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $546,000
Actual hours worked . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26,000
Standard labor-hours allowed for actual output (flexible budget) . . . 27,000
Direct labor price variance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $19,500 U
Actual variable overhead. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $132,600
Standard variable overhead rate per standard direct labor-hour. . . . . . $5.25
Variable overhead is applied based on standard direct labor-hours allowed.
Required
Compute the labor and variable overhead price and efficiency variances.
Step by Step Solution
3.46 Rating (172 Votes )
There are 3 Steps involved in it
Direct labor a Standard labor wage rate Actual Direct Labor Direct Labor Price Varia... View full answer