Question: The following data resulted from a time study taken on a horizontal milling machine: Mean manual effort time per cycle: 4.62 minutes. Mean cutting time

The following data resulted from a time study taken on a horizontal milling machine:
Mean manual effort time per cycle: 4.62 minutes.
Mean cutting time (power feed): 3.74 minutes.
Mean performance rating: 115%
Machine allowance (power feed): 10 percent.
Fatigue allowance: 15 percent.
What is the standard time for the operation?