Question: The following precedence diagram reflects three time estimates in weeks for each activity. Determine: a. The expected completion time for each path and its variance.
The following precedence diagram reflects three time estimates in weeks for each activity. Determine:
.png)
a. The expected completion time for each path and its variance.
b. The probability that the project will require more than 49 weeks.
c. The probability that the project can be completed in 46 weeks orless.
9-10-128 9-10-14 6.7 a) 13-13-13 14-18-26 6 8-8-8( 2 5-6-7 10.5-13-1 10 7-10-12 5
Step by Step Solution
3.48 Rating (161 Votes )
There are 3 Steps involved in it
Given We are given the following times optimistic most likely and pessimistic for each activity in the table below a Determine the expected completion ... View full answer