Question: The following table contains the activities for planning a wedding and the activity time estimates; however, the precedence relationships between activities are not included: Using
The following table contains the activities for planning a wedding and the activity time estimates; however, the precedence relationships between activities are not included:
.png)
Using your best judgment, determine the project network, critical path, and expected project duration. If it is January 1 and a couple is planning a June 1 wedding, what is the probability that it can be done on time?
Time (days) Activity Activity Description Obtain marriage license Select bridal attendants Order dresses 1 Select groomsmen Find and rent church Develop/print programs Address and mail invitations Compile RSVP list Determine reception menu Decorate reception hall 0.5 0.5 ion
Step by Step Solution
3.44 Rating (167 Votes )
There are 3 Steps involved in it
Activity Time ES EF LS LF Slack Variance a 933 0 933 0 933 0 544 b 483 933 1417 12083 12567 11150 13... View full answer