Question: The following table contains the activities for planning a wedding and the activity time estimates; however, the precedence relationships between activities are not included: Using

The following table contains the activities for planning a wedding and the activity time estimates; however, the precedence relationships between activities are not included:

The following table contains the activities for planning a wedding


Using your best judgment, determine the project network, critical path, and expected project duration. If it is January 1 and a couple is planning a June 1 wedding, what is the probability that it can be done on time?

Time (days) Activity Activity Description Obtain marriage license Select bridal attendants Order dresses 1 Select groomsmen Find and rent church Develop/print programs Address and mail invitations Compile RSVP list Determine reception menu Decorate reception hall 0.5 0.5 ion

Step by Step Solution

3.44 Rating (167 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Activity Time ES EF LS LF Slack Variance a 933 0 933 0 933 0 544 b 483 933 1417 12083 12567 11150 13... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

300-B-F-F-M (3534).docx

120 KBs Word File

Students Have Also Explored These Related Finance Questions!