The following table provides the information necessary to construct a project network and project crash data: a. Construct the project network.b. Compute the total allowable crash time per activity and the crash cost per week for each activity.c. Determine the maximum possible crash time for the network and manually crash the network the maximum amount.d. Compute the normal project cost

Chapter 8, Problems #30
The following table provides the information necessary to construct a project network and project crash data:

The following table provides the information necessary to construct a

a. Construct the project network.
b. Compute the total allowable crash time per activity and the crash cost per week for each activity.
c. Determine the maximum possible crash time for the network and manually crash the network the maximum amount.
d. Compute the normal project cost and the cost of the crashed project.
e. Formulate the general linear programming model for this network and solve it.
f. Formulate the linear programming crashing model that would crash this network by the maximum amount and solveit.

This problem has been solved!


Do you need an answer to a question different from the above? Ask your question!
Related Book For answer-question

Introduction to Management Science

11th Edition

Authors: Bernard W. Taylor

ISBN: 978-0132751919