Question: The following table provides the information necessary to construct a project network and project crash data: a. Construct the project network. b. Compute the total
The following table provides the information necessary to construct a project network and project crash data:
.png)
a. Construct the project network.
b. Compute the total allowable crash time per activity and the crash cost per week for each activity.
c. Determine the maximum possible crash time for the network and manually crash the network the maximum amount.
d. Compute the normal project cost and the cost of the crashed project.
e. Formulate the general linear programming model for this network and solve it.
f. Formulate the linear programming crashing model that would crash this network by the maximum amount and solveit.
Activity Time (weeks) Activity Cost Activity ,j) Activity Predecessor NoralCrash Normal Crash 20 24 14 10 8 $1.000 $1,480 1,200 1.400 1.190 820 730 20 (2, 4) (3, 4) 500 550
Step by Step Solution
3.39 Rating (168 Votes )
There are 3 Steps involved in it
a b Present normal critical path a d Normal critical path time 30 wk Crash critical path all ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (2 attachments)
300_606c7de9e8efa_209754.xlsx
300 KBs Excel File
300-B-F-F-M (3535).docx
120 KBs Word File
