Question: The following table gives the operation times and due dates for i ve jobs that are to be processed on a machine. Assign the jobs

The following table gives the operation times and due dates for i ve jobs that are to be processed on a machine. Assign the jobs according to the shortest operation time and calculate the mean flowtime.
The following table gives the operation times and due dates

DUE DATE (DAYS HENCE) PROCESSING JoB IME 6 days 5 101 102 7 days 103 104 105 5 days 4 days 9 days

Step by Step Solution

3.46 Rating (156 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

By the SOT rule the jobs would be assigne... View full answer