Question: The P-H Microchip Co. needs to undertake a major maintenance and renovation program to overhaul and modernize its facilities for wafer fabrication. This project involves
-1.png)
The estimated durations and costs of these activities are shown below in the left column.
-2.png)
(a) Find the earliest times, latest times, and slack for each activity.
What is the earliest finish time for the completion of the project?
(b) Use the Excel template for PERT/Cost in your OR Courseware to display the budget and schedule of costs based on earliest start times for this project on a single spreadsheet.
(c) Repeat part (b) except based on latest start times.
(d) Use these spreadsheets to draw a figure like Fig. 22.15 to show the schedule of cumulative project costs when all activities begin at their earliest start times or at their latest start times.
(e) After 4 weeks, activity B has been completed (with an actual cost of $200,000), activity A is 50 percent completed (with an actual cost to date of $200,000), and activity D is 50 percent completed (with an actual cost to date of $210,000). Construct a PERT/Cost report after week 4. Where should the project manager focus her attention to improve cost performances?
START FINISH Activity Estimated Duration Estimated Cost 6 weeks 2 weeks 4 weeks 5 weeks 7 weeks 9 weeks $420,000 180,000 540,000 360,000 590,000 630,000
Step by Step Solution
3.39 Rating (171 Votes )
There are 3 Steps involved in it
a The earliest finish time for this project is 20 weeks b c d e The ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
545-M-S-L-P (928).docx
120 KBs Word File
