Question: The time from when a patient is discharged from North Shore Hospital to the time the discharged patients bed is ready to be assigned to
.png)
a. Develop an x-chart to be used in conjunction with an R-chart using 3Ï limits to monitor the bed turnaround times and indicate if the process is in control using these charts.
b. Is the hospital capable of consistently achieving bed turnaround times of 120 minutes ±15 minutes without improving theprocess?
Day 127 140 112 223 181 103 146 104 136 145 84 169 216 190 14B 157 142 166 Bed Turnaround Times (min) 135 155 128 135 155 158 135 122 158 163 146 152 124 178 205 151 102 178 167 122 154 160 145 167 115 137 106 125 208 163 103 144 126 10 159 204 158 152 138 134 211 20 21 98 133 212 180 160 131 165 24 25 126 156 202 157 108 138 156 144 184 138 150 165 106 155 148 29 142
Step by Step Solution
3.44 Rating (157 Votes )
There are 3 Steps involved in it
a Day R 1 14300 40 2 13900 33 3 11233 31 4 17067 88 5 16533 26 6 13533 55 7 14933 32 ... View full answer