Question: The Yankee Machine Shop currently has three machines working in Work Center 111, eight hours per day, five days per week, a utilization rate of
The Yankee Machine Shop currently has three machines working in Work Center 111, eight hours per day, five days per week, a utilization rate of 90 percent, and an efficiency rate of 90 percent.
(a) Calculate the available capacity.
(b) Is the available capacity enough to complete the orders given in Problem 19 that are already scheduled in Work Center 111? If not, how much additional capacity is needed?
Step by Step Solution
3.58 Rating (159 Votes )
There are 3 Steps involved in it
a Available weekly capacity 3 ... View full answer