Question: This is a variation of Problem 5-5 modified to focus on the completed contract method. In problem 5-5, In 2011, the Westgate Construction Company entered
This is a variation of Problem 5-5 modified to focus on the completed contract method.
In problem 5-5, In 2011, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2013. Information related to the contract is as follows:
.png)
Westgate uses the percentage-of-completion method of accounting for long-term construction contracts.
Required:
Complete the requirements of Problem 5-5 assuming that Westgate Construction uses the completed contractmethod.
2011 2012 2013 2400000 36000005 2200000 Cost incurred during the year Estimated costs to complete as of year-end 56,00,000 20,00,000 Billings during the year Cash collections during the year 20,00,00040,00,00040,00,000 18,00,000 36,00,00046,00,000
Step by Step Solution
3.59 Rating (156 Votes )
There are 3 Steps involved in it
Requirement 1 Year Gross profit recognized 2011 0 2012 0 2013 1800000 Total gross profit 1800000 Req... View full answer