Question: Thompson Construction Company soon will begin work on a building for Echelon Savings Bank. Work on the building was started by another construction firm that
.png)
Required:
(1) Prepare the PERT network.
(2) Identify the critical path and determine the expected time in weeks for the project.
(3) Explain the effect on the critical path and expected time for the project if the company is not required to apply for and obtain the waiver to add new materials.
Activity Code Activity Description Estimated Time 2-3 3-5 3-4 4-5 5-6 6-7 Complete interior partitions.... Obtain on-site work permit.. Repair damage done by vandals. Inspect construction materials left on site.. Order and receive additional construction materials... Apply for waiver to add new materials... Obtain waiver to add new materials....m (in weeks) 4 2 4 2
Step by Step Solution
3.46 Rating (178 Votes )
There are 3 Steps involved in it
1 PERT network 2 Alternate paths and times and the critical path and the expect... View full answer