Question: Consider the following activity information and the constraint that the project must be completed in 16 weeks. In addition, activities c, f, h, and i
-1.png)
In addition, activities c, f, h, and i may be crashed as follows. Assume partial crashing.
-2.png)
Find the best schedule and itscost
PA-nnnabccdg 368750456 234555677 vt 1 1 1 2 3 4 4 5 6 abcdefgh i Crash Time Additional Activity(weeks) Cost per Week $40 10 30
Step by Step Solution
3.35 Rating (173 Votes )
There are 3 Steps involved in it
Activity Crash Wk Crash Wk C 1 4000 F 4 2000 H 3 1000 ... View full answer