Ting Group began work on a 7,000,000 contract in 2019 to construct an office building. During 2019,

Question:

Ting Group began work on a ¥7,000,000 contract in 2019 to construct an office building. During 2019, Ting Group incurred costs of ¥1,700,000, billed its customers for ¥1,200,000, and collected ¥960,000. At December 31, 2019, the estimated additional costs to complete the project total ¥3,300,000. Prepare Ting's 2019 journal entries using the percentage-of-completion method.
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Intermediate Accounting IFRS

ISBN: 978-1119372936

3rd edition

Authors: Donald E. Kieso, Jerry J. Weygandt, Terry D. Warfield

Question Posted: