Question: Tooltron Manufacturing uses a Kanban system for a component. Daily demand is 425 units. Each container has a combined waiting and processing time of 1.5
Tooltron Manufacturing uses a Kanban system for a component. Daily demand is 425 units. Each container has a combined waiting and processing time of 1.5 day. If the container size is 35 and the alpha value (a) is 12 percent, how many kanban card sets should be authorized? What is the maximum authorized inventory?
Step by Step Solution
3.35 Rating (158 Votes )
There are 3 Steps involved in it
Using Equation 171 we have K dp w 1 C 42515 1 12 35 204 or 21 Kanban cards should ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
1206-B-M-L-O-M(6313).docx