Question: Tovi Landscaping plants grass seed as the basic landscaping for business campuses. During a recent month, the company worked on three projects (Bose, Larkin, and
Tovi Landscaping plants grass seed as the basic landscaping for business campuses. During a recent month, the company worked on three projects (Bose, Larkin, and Torres). The company is interested in controlling the materials costs, namely the grass seed, for these plantings projects.In order to provide management with useful cost control information, the company uses standard costs and prepares monthly variance reports. Analysis reveals that the purchasing agent mistakenly purchased poor-quality seed for the Bose project. The Larkin project, however, received higher-than-standard-quality seed that was on sale. The Torres project received standard-quality seed; however, the price had increased and a new employee was used to spread the seed.Shown below are quantity and cost data for each project.

Instructions(a) Prepare a variance report for the purchasing department with the following columns:(1) Project, (2) Actual pounds purchased, (3) Actual price, (4) Standard price, (5) Price variance, and (6) Explanation.(b) Prepare a variance report for the production department with the following columns:(1) Project, (2) Actual pounds, (3) Standard pounds, (4) Standard price, (5) Quantity variance, and (6)Explanation.
Standard Costs $1,150 1,025 1,200 Actual Costs $1,175 Total Variance Project Bose Larkin Torres Total variance Quantity 460 lbs. 410 Quantity 500 Ibs. $ 25 U 65 F 400 500 960 1,300 100 U $ 60 U 480
Step by Step Solution
3.45 Rating (161 Votes )
There are 3 Steps involved in it
a TOVI LANDSCAPING Variance Report Purchasing Department For the Current Month Proj... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
54-B-M-A-S-C (232).docx