Question: Universal Motors installed a mixed model assembly line at its Huntsville plant last year when demand for SUVs was still strong. With the rising gas
a. Design a production sequence that will meet demand and level production of the various models.
b. How many times will that sequence be repeated per day?
c. Explain how the sequence you propose allows quicker adjustments to demand changes. What impact does it have on component demand?
Step by Step Solution
3.37 Rating (150 Votes )
There are 3 Steps involved in it
a CVCSCVC b Repeat 25 times a day c By spreading out model production an... View full answer