Question: Use the following activities and their three duration estimates (in days) to do the following: a. Determine the expected duration of the project. b. Calculate
Use the following activities and their three duration estimates (in days) to do the following:
a. Determine the expected duration of the project.
b. Calculate the probability' that the project will take at least 18 days.
.png)
Durations Path Activity abc 10 def
Step by Step Solution
3.45 Rating (165 Votes )
There are 3 Steps involved in it
a b Activity a b d e f Path abc Expected def Duration to 4tmtp 6 5 817 533 ... View full answer