Question: Use the following information to construct a Gantt chart in MS Project. What is the expected duration of the project (critical path)? Assume the project
.png)
Activity Duration (in Days) Predecessors completed (Day 16) None 100% 100% 100% 14% 10 B, C 33% E, F 0%
Step by Step Solution
3.44 Rating (157 Votes )
There are 3 Steps involved in it
The projects duration is 32 days and the critical path is ACDEG The t... View full answer