Question: Using the accompanying diagram, do the following: a. Draw a tree diagram for the scissors. b. Prepare an MRP plan for scissors. Lead times are
Using the accompanying diagram, do the following:
a. Draw a tree diagram for the scissors.
b. Prepare an MRP plan for scissors. Lead times are one day for each component and final scissor assembly, but two days for the plastic grips. Six hundred pairs of scissors are needed on day 6. Note:
There are 200 straight blades and 350 bent blades on hand, and 40 top blade assemblies on hand.
Use lot-for-lot ordering for all items.
.png)
Bent plastic grip Top Straight Bent blade Bottom Straight plastic grip
Step by Step Solution
3.36 Rating (152 Votes )
There are 3 Steps involved in it
Given a Draw a product structure tree tree diagram for the scissors Lead times are 1 day for each component and final scissor assembly but 2 days for the plastic grips 600 scissors are needed on Day 6 ... View full answer