Question: Using the following figure, perform resource leveling. Assume that each task can be performed independently of the othertasks. Task 1 (2 workers) Task 2 (1
.png)
Task 1 (2 workers) Task 2 (1 worker) Task 3 (3 workers) I Task 4 (2 workers) Task 5 (1 worker) Task 6 (3 workers) Day 1 2 3 456 78910 Workers 6664 2 3 3 433
Step by Step Solution
3.49 Rating (179 Votes )
There are 3 Steps involved in it
One possible solution would be Step 1 Delay Task 1 to start after Task 2 is complete S... View full answer