Question: Using the information in P11-3B, compute the overhead controllable variance and the overhead volume variance. Data From P11-3B, Zimmerman Clothiers manufactures womens business suits. The
Using the information in P11-3B, compute the overhead controllable variance and the overhead volume variance.
Data From P11-3B,
Zimmerman Clothiers manufactures women’s business suits. The company uses a standard cost accounting system. In March 2014, 15,700 suits were made. The following standard and actual cost data applied to the month of March when normal capacity was 20,000 direct labor hours. All materials purchased were used in production.

Overhead is applied on the basis of direct labor hours. At normal capacity, budgeted fixed overhead costs were $125,000, and budgeted variable overhead costs were $63,000.
Instructions
(a) Compute the total, price, and quantity variances for (1) materials and (2) labor.
(b) Compute the total overhead variance.
(c) Which of the materials and labor variances should be investigated if management considers a variance of more than 5% from standard to be significant?
Standard (per unit) 5 yards at $6.75 per yard Cost Element Actual $547,200 for 76,000 yards ($7.20 per yard) $165,760 for 14,800 hours ($11.20 per hour) $120,000 fixed overhead Direct materials Direct labor 1.0 hours at $11.45 per hour 1.0 hours at $9.40 per hour (fixed $6.25; variable $3.15) Overhead $49,000 variable overhead
Step by Step Solution
3.37 Rating (169 Votes )
There are 3 Steps involved in it
Overhead controllable varian... View full answer