Question: Using the information in Problem 14.3, construct a gross material requirements plait. In Problem 14.3, The demand for subassembly S is 100 units in week
In Problem 14.3, The demand for subassembly S is 100 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 Unit of V, 2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z.
Step by Step Solution
3.44 Rating (163 Votes )
There are 3 Steps involved in it
Gross material requirements plan Week Lead Time Item 1 2 3 4 5 6 7 8 weeks S Gross req 100 Order r... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
256-B-M-L-O-M (1945).docx
120 KBs Word File
