WCM Builders enters into a contract to build a shopping mall in 2011 for $6,000,000. Completion of

Question:

WCM Builders enters into a contract to build a shopping mall in 2011 for $6,000,000. Completion of the mall is expected to take 2 years and cost WCM $3,600,000. Upon signing the contract, WCM receives $600,000. During 2011, WCM incurs costs of $1,200,000 and receives a $1,000,000 progress payment. WCM’s forewoman estimates that the job is 50% complete at the end of 2011. How much income mustWCM recognize in 2011 from the work done on the mall?


Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer: