Question: What is the probability that a project with the following precedence network will take more than 10 weeks to complete if the activity means and
-1.png)
-2.png)
Standard Deviation 1.3 1.0 1.6 Activity Mean End
Step by Step Solution
3.34 Rating (163 Votes )
There are 3 Steps involved in it
Path Expected Duration Std Dev z ... View full answer