Question: What settlement would you expect at the over consolidated site in Problem 8.16 if the fill to be constructed were 4 m thick?
What settlement would you expect at the over consolidated site in Problem 8.16 if the fill to be constructed were 4 m thick?
Step by Step Solution
★★★★★
3.45 Rating (164 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
v 4 m 18 Mgm 3 981 ms 2 7063 kPa vo 15 kPa p 38 kPa From ... View full answer