Question: When resource-leveling a project, a number of heuristics can help us prioritize those activities that should receive resources first. Explain how each of the following
When resource-leveling a project, a number of heuristics can help us prioritize those activities that should receive resources first. Explain how each of the following heuristics works and give an example:
a. Activities with the smallest slack
b. Activities with the smallest duration
c. Activities with the lowest identification number
d. Activities with the most successor tasks
e. Activities with requiring the most resources
a. Activities with the smallest slack
b. Activities with the smallest duration
c. Activities with the lowest identification number
d. Activities with the most successor tasks
e. Activities with requiring the most resources
Step by Step Solution
★★★★★
3.38 Rating (164 Votes )
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
a Those activities that have the smallest amount of slack are given priority for resources This is d... View full answer
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
Document Format (1 attachment)
663-B-M-L-P-M (2192).docx
120 KBs Word File