Question: Why might a probabilistic estimate of a projects completion time based solely on tire variance of the critical path derived using the expected activity' durations

Why might a probabilistic estimate of a project’s completion time based solely on tire variance of the critical path derived using the expected activity' durations be misleading? Under what circumstances would it be acceptable?

Step by Step Solution

3.43 Rating (156 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Nearcritical paths even though have smaller average duration may have la... View full answer