Question: You are the coordinator of a moderately complex project. The following problems have arisen during the execution phase of previous projects with the resulting delays
.png)
Problem A Late dellvery from suppliers B Last-minute redesign of assembly Delay (days) 36 due to customer change of specification Suppliers fail to meet the quality levels required in goods supplied C 41 D Schedule did not leave enough time for testing Components did not fit together when assembled Customer rejected initial trial system Engineer left team during the project Office move was scheduled for during the completion phase E 6 F 12 G 16 H J Hauliers' firm sacked by customer due to dispute over delivery times
Step by Step Solution
3.43 Rating (188 Votes )
There are 3 Steps involved in it
Pareto Analysis would help in this instance with the output as shown ... View full answer